Structural Failures – A Reflection of Societal Failure

Some structural failures are caused by the most stealthy human factors: corruption and greed. This is a situation that is far worse in the third-world countries where the use of sub-standard materials, faulty construction methods and cutting corners around standard specifications is the norm.

In this article, the influence of societal failure on structural failures will be explored using the events surrounding the collapse of the Sampoong Superstore in South Korea in 1995.

Sampoong Store

Originally designed as an office building, the five-storey, bright pink superstore would not be constructed without controversies. It was constructed on landfill, and Woosung Construction designed the building’s foundations and basements. Issues emerged as Woosung rejected planned changes to the use of the building – it was to be modified from office to retail and an additional floor, a fifth floor to be added. Woosung, insistent on these changes, was sacked and replaced by Sampoong’s in-house contractors. The in house contractors would carry on with construction, eventually completing and opening up the building in December 1989 after inspections, seemingly satisfied it met all the required specifications.

All went fine for five and a half years, but by mid-1995 it became obvious that everything about the structure was really wrong. Major cracking in the roof slab was found on the morning of 29 June, 1995.  At some point earlier, heavy air-conditioning systems, which were initially situated on the east side of the building, were moved west due to noise complaints. The units were actually dragged onto the roof floor, instead of being raised by crane. It would transpire that the slab had just one-quarter of the capacity needed to accommodate the units and that the roof had been heavily compromised. At column locations, cracks had opened up to 25 mm wide.

Engineers were eventually brought in to investigate, and they recommended the evacuation of the building. However, executives at the organization agreed otherwise. Over the course of the day, the cracks worsened and spread. The air conditioning systems were switched off as vibration seemed to be making it worse. At 6 pm the building could take no more, and the 91m long north wing of the store suddenly collapsed (Figure 1). Only the two end walls of the structure remained standing. There were 498 fatalities.

Describes the collapse of sampoong superstore
Figure 1: Structural failure of Sampoong Superstore, South Korea

Investigation into the Failure

Whilst it could’ve been argued that this structural failure was actually set in motion by the movement of the air conditioning units, however, bribery and corruption had ensued a deficient structure from the outset. One of the main problems was the decision to modify the function of the building from office to retail without following the due process of reassessing the structural design, which consisted of columns and slabs without supporting beams (flat slabs). The transition to retail resulted in major limitations being added, such as the construction of escalators requiring wide openings to be made in the flat slabs. In spite of these, it was indeed, the replacement of the proposed skating rink on the fifth floor with the conventional Korean restaurant that created the major problem.

Traditional Korean restaurants have no chairs –  patrons normally sit on the floor. So, when the decision was made to add in-floor heating, this involved the construction of a 900 mm deep concrete floor. This extra concrete added substantial mass to the structure and raised the dead load on the fifth floor by 35%. To make matters worse, columns were either completely removed or relocated to suit the architectural needs of the building, leading to a condition where columns no longer aligned with those below. The flat slab was now playing a critical structural role in transferring column loads between the floors. At the end of the day, the cause of the failure was the modifications brought on by the “illegal modification of the architectural style and use of the structure”.

Although the modifications may have contributed to a structural failure, these unlawful modifications were just the tip of the iceberg when it came to non-compliance with structural specifications. For a start, the 890 mm thick columns were actually 610 mm thick. They had just 8 as opposed to 16, reinforcing bars. In other instances, reinforcement were being omitted. Concrete strength was just 18MPa when 21MPa was specified. And these changes were made possible by corruption – 12 local building authorities were found guilty of taking bribes for approval of modifications and issuing temporary certificates of use. They were paid in excess of US$ 17,000.

Wider Implications

The structural failure and loss of life caused outrage in Korea, leading to an investigation of the construction industry in South Korea. The investigation found an endemic level of corruption, which was historical. Korea’s building industry was thriving in the 1980s, and there was tremendous pressure on companies to perform – a situation compounded by a government veto that prohibits contracts from being signed overseas. Then Seoul was awarded the 1988 Olympic Games, further stressing the situation. Such an environment was ripe for abuse, and the construction of the Sampoong Superstore occurred in the midst of this rush.

Though it was to become the most noticeable disaster, the issue was even wider: the South Collapse of Sampoong Superstore, South Korea. The survey of high-rise buildings by the Korean government indicated that only 2% met the standards; 84% needed repairs and 14% deemed unsafe and required reconstruction.

Legacies

The Sampoong Superstore structural failure teaches us that a malfunction happens every once in a while and has an impact well beyond the rubble and the devastating loss of life. These shortcomings cause us, as a society, to look more deeply at ourselves. Sampoong collapse exposed widespread corruption in Korea in the 1990s, however, what is the situation in the third world countries today? There is more than meets the eye in the construction industry of a third world country! In fact, to say that the level of corruption in the construction industries of developing countries is endemic would be a gross understatement, it’s indeed ” more than a pain in the rear” Almost all causes of structural failures in third world nations, particularly Nigeria can be traced back to bribery and corruption.

In 2019 alone, over 43 building collapse cases was recorded in Nigeria and over 36,000 potential structural failures waiting to happen. The journey is very far and long and far from complete especially for those in the third world countries but the Sampoong superstore tragedy should remind us that any time we open our wallets in today’s globalized economy, the transaction is not just monetary but also moralistic.

Also See: The Collapse of Willow Island Cooling Tower

Sources & Citations

Delatte N. J. (2009) Beyond structural failures: forensic case studies for civil engineers, Reston, USA: ASCE Press

Building Collapse Prevention Guild -2019 (BCPG) (Annual Report)

Thank you, please share!

58 Replies to “Structural Failures – A Reflection of Societal Failure”

Leave a Reply

Your email address will not be published. Required fields are marked *